What to expect on construction day!
DAY 1
What We Do
Please have everything within a 50’ radius out of the way (move furniture, cover plant beds, take down string lights, etc.).
Our foreman will meet with you if you are home and walk through the project with you.
If you are not home for the walk-through we just ask that you check the forms when you are home that night.
Remove any fence posts, landscaping or any other sort of obstruction in the way that you have discussed with your sales contact.
Use a plywood machine path and remove any concrete, deck, pavers or other material that needs to be removed using a front loader.
Set the forms of your project and compact a 4” base of limestone or recycled crushed concrete.
If you are having piers installed, they will drill down below the frost line and set 6” pipe for the piers.
If anything needs tweaked, please let us know by 9pm that night.
We ask for 50% of payment when they arrive to start on Day 1.